Skip to main content

Table 9 Summary of system design and impacts for infrastructure after the 2011 PCC-VC eruption

From: Impacts to agriculture and critical infrastructure in Argentina after ashfall from the 2011 eruption of the Cordón Caulle volcanic complex: an assessment of published damage and function thresholds

Infrastructure

Towns

Design

Impacts

Main issues

Electricity

Villa la Angostura

Not connected to national grid; 6.1MW thermal generation plant

Flashover on 13.2 kV, 380 V, and 220 V networks due to damp ashfall; Dry ashfall clogged air intakes for the thermal plant resulting in precautionary shutdowns

Flashover; air intake clogging

Bariloche

Single transmission line and one grid exit point from national grid; Outdoor GXP substation

Whole town lost power for 8 h, with some not reinstated for 24 h after the initial ashfall; power cuts due to GXP substation suffering flashover due to ash; contamination of switches and busbars; diesel and gas generators were deployed around the town but the air intakes became blocked with ash

Flashover; air intake clogging; switch abrasion; generator blockage

Jacobacci

Single transmission line and one grid exit point from national grid; Outdoor GXP substation

Some flashover caused intermittent power cuts to the town (usually for only a few hours); Tripping of switches due to flashover and abrasion of metallic components

Flashover; switch abrasion

Water Supply

Villa la Angostura central system

Town centre supplied by Lomas del Correntoso treatment system. Water is extracted from Lago Correntoso and Lago Nahuel Huapi then pumped up an 80 m rise to the WTP. An initial filtration step is followed by pressure sand filtration then chlorindation then gravity fed to households.

The eruption increased the level of suspended ash in the lake, which caused high levels of wear and tear on pumping equipment. Power outages also caused problems for this system.

Turbidity increase; damage to pumping equipment

Villa la Angostura peripheral systems

A range of smaller systems based on intakes from streams or the lake. Systems are generally gravity-fed. System designs vary considerably, but in general the stream-fed systems are poorly maintained and do not achieve a good level of sediment removal prior to chlorine dosing. Water supplied to households may not contain adequate chlorine residuals.

Stream-fed systems were severely affected by the eruption, with intake structures inundated with ash. These systems continued to experience problems in rainy conditions when further ash was washed downstream. Some systems have been abandoned.

Damage to intake structures; turbidity increase; other contamination of raw water source; clogging of filters; overall system failure

Bariloche central system

Bariloche’s central water treatment plant has an intake in Lago Nahuel Huapi. Water is pumped up a 150 rise to storage tanks. The treatment process does not include a preliminary coagulation/flocculation step as intake water is normally very low in turbidity (0.2–0.4 NTU). Filtration is through open-air slow sand filters prior to chlorination.

The eruption increased the level of suspended ash in the lake, which not only caused accelerated wear and tear on pumping equipment but also allowed ash to enter the treatment plant (both via the intake and by direct fallout) where it clogged open sand filter beds. A greatly increased level of maintenance was required to manage these problems and remain in production. A city-wide power outage caused an interruption to water production.

Turbidity increase; damage to pumping equipment; clogging of filters

Bariloche peripheral systems

Similar to range of smaller systems in Villa la Angostura; outlying neighbourhoods supplied by smaller systems with intakes from springs, streams and the lake, with wide variety of treatment system design.

Effects were similar to, though less severe than, for Villa la Angostura.

Damage to intake structures; turbidity increase; clogging of filters

Jacobacci

17 groundwater wells with well-head pumps enclosed in pumphouses; water then chlorinated and distributed

This system is completely enclosed and thus proved resilient to the ashfall. However problems were experienced with high water demand as the town was repeatedly subjected to wind-remobilised ash and additional water was required for clean up

A sustained increased water demand

Waste water

Villa la Angostura

Not investigated during field visit

 

-

Bariloche

Treatment plant 4.3 km east of the city; pumped to plant then screened through 25 mm bars, pumped through a decanter, then through a anaerobic tank before entering the biological reactor (Nocardia spp. Bacteria), finally wastewater sludge is separated and taken to the dewatering plant

Solids coming into the plant increased from 4500 mg/L to 8000 mg/L in the 3 days after the eruption due to ash contamination; sewer lines and storm drains were meant to be separated but sometimes illegally connected which meant large volumes of ash entered the system; power cuts meant that pumping stations without generators stopped; pump impellers had accelerated wear; 1 m of ash accumulated in the bottom of the 4.5 m deep biological reactor which reduced the plants capacity

Blockages of stormwater catchpits and sewer lines and junctions; accelerated wear and tear to sewage pump impellers; power outages affected pumping

Jacobacci

Not investigated during field visit

 

-

Roading

Villa la Angostura

Asphalt main roads, unsealed secondary routes

Route 231 (asphalt) connecting Villa la Angostura with Bariloche was closed after the eruption for a day, then reopened but with speed restrictions; the Samore Pass border between Chile and Argentina was closed for several weeks after the eruption due to the thickness of ash recieved (>300 mm); drivers reported a loss of traction, inability to see road markings, and some issues with air filters becoming clogged

Road closures; road markings not visable; loss of traction; air filter clogging

Bariloche

Asphalt

Route 40 (asphalt) the main road into Patagonia was closed for two days after the eruption; main road within the town were covered with 50 mm of ash therefore authorities recommended that cars stayed off the road

Road closures; road markings not visable; loss of traction; air filter clogging

Jacobacci

Predominantly unsealed

Visibility an issue due to wind remobilisation, this prevented almost all driving and clean up for the first week; road between Jacobacci and Bariloche closed for a few days, then reopened to limited traffic at low speeds

Road closures; low visibility; road markings not visable; loss of traction; air filter clogging

Airports

Bariloche

Fourth largest airport in Argentina; located 13 km outside of Bariloche; airport land covers 1,810 Ha with a 2,400 m runway

Airport was closed for a month due to ashfall; approximately 1000 tonnes of ash was deposited onto airport land; when the airport reopened some airlines (LAN Chile and Aerolinas Argentina) did not recommence flights due to fears around ashfall and accurate forecasting; full service resumed on 20 December 2011

Airport closure; airlines reluctant to resume flights